TOWARDS AN INTEGRATED SCRIPT FOR RISK AND VALUE MANAGEMENT

 

S. D. GREEN

Department of Construction Management & Engineering, The University of Reading, UK.

 

 

ABSTRACT

It is contended that the current conceptual distinction between risk management and value management is unsustainable.  The origins of the two traditions are reviewed and critiqued from a postmodernist perspective.  It is concluded that they differ primarily in terms of their rhetoric, rather than their substantive content.  Insights into the current practice of risk and value management are provided by considering their enactment in terms of ‘performance’. The scripts for such performances are seen to be provided by the accepted methodologies which determine the language to be used and the roles to be acted out. A coherent integrated script for risk and value management can be provided by the methodology known as strategic choice, which replaces the language of ‘risk’ and ‘value’ with that of ‘uncertainty’. The benefits of adopting this alternative script are illustrated through six case studies.

 

Keywords: risk management, value management, postmodernism, dramaturgical metaphor, rhetoric, strategic choice.

 

 

INTRODUCTION

 

Risk management and value management are both widely recognised to be an essential part of best practice [1] [2].  Although significant attention has been directed to the two topics in isolation, there has as yet been little progress in the development of an integrated approach.  The separation of the two disciplines is well illustrated by the way in which the Construction Industry Research and Information Association (CIRIA) and HM Treasury have both published separate guides to risk management [3] [4] and value management [5] [6].  In developing the argument in support of the need for an integrated process, it is initially necessary to establish the intellectual origins of the two disciplines.  The case will be made that the two disciplines only really differ in terms of the rhetoric in which they are presented. It will then be suggested that an alternative script for integrated risk and value management can be provided by the strategic choice approach. The benefits of this approach will be illustrated through a summary of six case studies. The case will also be made for a continuous process of intellectual deconstruction of established concepts as an essentially requirement for an innovative and reflexive construction industry.

 

 

VALUE MANAGEMENT

 

Two schools of thought can be identified in the value management literature.  The first follows the tradition of systems engineering and seeks to achieve given identified functions at minimum cost [7] [8] [9].  This approach tends to be implemented by an external team in response to a projected cost overspend and is usefully labelled ‘value engineering’ [10].  It is essentially a technical activity that seeks efficient means of achieving known ends. 

            The second school of thought focuses on the strategic interface between client organisations and construction projects [11] [12].  From this point of view, the primary purpose of value management is to resolve ambiguity and establish a shared commitment to a common set of design objectives [5].  The emphasis no longer lies on the technical evaluation of design alternatives, but on a process of communication and consensus building with the active participation of the project stakeholders. Within this school of thought, value management is primarily perceived as an aid to the briefing process rather than a technique of cost reduction. Whereas value engineering is characterised by an underlying positivism, the emerging ‘second generation’ of value management owes its allegiance to an underlying epistemology of social constructivism [13].  Sources such as Barton [11] are especially notable in emphasising the role of the facilitator rather than the application of mechanistic techniques.

            It is useful to classify the above two approaches to value management as ‘hard’ and ‘soft’.  Similar distinctions have been made within the more established fields of operational research [14] and systems theory [15].  The same two alternative ‘hard’ and ‘soft’ approaches are also evident within the construction risk management literature.

 

 

RISK MANAGEMENT

 

The hard paradigm

The established techniques of risk management are well described in Chapman and Ward [16], Flanagan and Norman [17] and Raftery [18].  Such sources directly reflect the ‘hard’ paradigm of value engineering in that they are primarily concerned with quantitative techniques.  The emphasis given by Raftery [18] to the role of external ‘experts’ in the risk management process is especially notable. The intellectual origins of these approaches can be traced back to probability theory and the concept of ‘risky utility’ [19]. It is the concept of risky utility that underpins the frequently described techniques of expected monetary value (EMV) and expected net present value (ENPV).  The dominant assumption behind these approaches is that risk relates to the uncertainty of future outcomes.  It is further assumed that the stakeholders can agree on a common interpretation on the likelihood of their occurrence.  In many respects, previous critiques of ‘hard’ value engineering are also directly relevant to the corresponding paradigm of risk management. Both approaches are limited to problem contexts that are technical, static and well-defined.  It is invariably assumed that the definition of the ‘problem’ is in itself unproblematic. Traditional risk management is too often limited to 'technical' issues. The definition of 'technical' frequently embraces financial issues and hazardous operations. Nevertheless, the 'soft' factors relating to the ways in which stakeholders think, behave and interact are at best under-emphasised, and at worst ignored.

 

An emerging alternative paradigm

The established texts on risk management [16] [17] [18] are further notable in the way that they tend to be prescriptive rather than descriptive.  The included case studies tend be to highly idealised and divorced from the organisational context from which they were derived. Those few sources which set out to describe current practice are notably at odds with the prescriptive literature, e.g. [20] [21].  However, there is evidence that a tentative ‘soft’ paradigm of risk management is gaining ground. Sources such as Godfrey [3] place much less emphasis on the use of quantitative techniques, stressing the team nature of risk management and the corresponding importance of an independent facilitator. The risk management process is no longer conceptualised in terms of ‘decision-making’, but as a means of continuous learning.  In this respect, Godfrey’s approach to risk management echoes many of the characteristics of ‘soft’ value management.  Indeed, it is notable that both are advocated primarily as a means of resolving conflict within the project team.

 

The epistemology of risk management

On the basis of the available literature, it would seem that the emerging soft paradigm of risk management remains less conceptually developed than its equivalent within value management.  Certainly within the domain of construction management, there is a notable absence of any risk management approaches laying claim to a guiding epistemology of social constructivism. This is not to say that the hard paradigm is without its critics. Mak [22] has challenged the paradigm of quantitative risk management and the validity of its underlying reliance on normative Bayesian statistics.  Nevertheless, the articulated alternative falls some way short of social constructivism.  Mak emphasises the use of heuristics in searching out solutions that are ‘good enough’. The approach therefore follows Simon’s [23] concept of satisficing and as such is based on a post-positivist position.  The ontological position of naive realism is seemingly weakened to one of critical realism, see [24].  Whilst Mak seems to accept that optimal solutions cannot be identified due to the limitations of human perception, he still seems to believe that they exist at least in theory. 

           

The need for a broader framework

Much of the uncertainty which occurs during construction cannot be construed as ‘technical’.  This is especially true for the earlier stages of the project life-cycle, where decisions need to span the boundary between the construction project and the broader environment. The context for many construction projects is provided by multi-faceted client organisations that comprise several different interest groups whose objectives often differ [25]. Within this context, risk management can no longer be considered to be a narrow activity that is applied to ‘technical’ issues in isolation of other factors.  The process of risk management therefore only becomes meaningful through the active participation of the client’s project stakeholders. Effective risk management of this nature depends less upon probabilistic forecasting and more upon the need to maintain a viable political consistency within the client organisation.  It is notable that there is as yet no recognised framework that embraces both the notion of technical risk with the less tangible uncertainties that characterise the strategic interface between construction projects and client organisations.

 

 

THE CASE FOR INTEGRATION

 

The continued acceptance of risk and value management as two discreet disciplines can be traced back to neo-classical economics and decision theory.  Once stripped of its popularist rhetoric, the guiding intellectual framework for value management can be seen to be provided by the ‘theory of riskless choice’, otherwise labelled the ‘fundamental theorem of utility’ [26].  It is the notion of ‘riskless utility’ which provides the basis for multi-attribute utility theory (MAUT) and the associated weighted preference methods which are so popular within the value management literature, e.g. [5] [6] [27].

            In contrast, the guiding intellectual framework for risk management stems from the ‘theory of risky choice’. This was originally developed from von Neumann and Morgenstern’s (1947) concept of ‘risky utility’, as defined within the context of hypothetical gambles.  At the time, the supposed discovery of measurable utility caused considerable furore within the economics community.  Subsequent contributions by Ellsberg [28] and Edwards [29] served to classify the two types of utility into entirely different concepts.  Hence the distinction between the ‘theory of risky choice’ and the ‘theory of riskless choice’ as initially labelled by Edwards [29].  Modern writers on decision theory perpetuate this distinction by referring to value functions when utility is used in the neo-classical sense (i.e. in the absence of uncertainty) and utility functions when used in the risky sense.  It is their respective allegiance to these two different traditions that primarily distinguishes value management from risk management.  However, even within the context of decision theory, an increasing number of commentators have questioned the extent to which this distinction is meaningful.  Fishburn [26] suggests that the phrase ‘decision making under certainty’ is simply an abbreviation of ‘decision making in which uncertainty, whatever form it may take, is suppressed and not given explicit recognition’.  Von Winterfeldt and Edwards [30] have also expressed doubts whether the distinction between ‘utility’ and ‘value’ is valid:

 

In our opinion, the distinction between value and utility is spurious because....there are no sure things, and therefore values that are attached to presumably riskless outcomes are in fact attached to gambles.

 

In the light of the above, it is valid to question whether the continued distinction between value management and risk management is meaningful.  The CIRIA report on risk management suggests that ‘the techniques of risk management are similar to those used in the management process known as value management, outputs from each being closely linked and inter dependent’ [3].  If the techniques really are similar, and there is no such thing as a ‘riskless decision’, there would seem to be little logic in defining value management and risk management as separate services.

 

 

A POSTMODERNIST INTERPRETATION

 

Reality construction through language

A postmodernist perspective provides an alternative reading of the current practices of risk and value management. The advocates of postmodernism contend that the world is constituted by shared language and can only be understood through particular forms of discourse [31] [32]. In other words, humans experience the world through a given set of words and concepts [33]. This is in direct opposition to the modernist view that language describes something which already exists ‘out there’.  From a postmodernist perspective, the expressions ‘risk’ and ‘value’ do not relate to any sort of external reality, but provide the language through which managers construct their own reality. The contention is that neither value management nor risk management possess any substantive content other than the language within which there are presented. They are only implemented as discrete activities because there is an expectation that ‘risk’ and ‘value’ should be managed separately. This expectation is created by the literature that has fabricated the nonsense that value management and risk management exist independently. Note that neither of these actually ‘exist’ at all, they have merely been constructed as separate entities. A postmodernist interpretation also serves to challenge the grandiose claims often made in favour of 'methodology'. A methodology becomes a 'script' that uses particular forms of rhetoric to be persuasive. Such an interpretation would question the argument that different methodologies are characterised by different assumptions. The notion that 'soft' and 'hard' approaches are characterised by different epistemological positions would seem to be somewhat contrived. A more defendable position is that different methodologies are characterised by different forms of rhetoric.

 

Motivations and benefits

It is interesting to consider the motivations that drive practitioners to adopt initiatives such as risk management and value management.  A common motivation will be a desire to demonstrate to clients and colleagues that they are efficient and up-to-date in the latest management techniques.  Apart from issues of image, an organisation could realistically benefit through a more participative and reflective means of decision-making.  However, both of these potential benefits are extremely fragile. The arena for the desired participation is too often limited to the risk (or value) management workshop.  The decision to implement a ‘participatory’ approach is invariably made unilaterally by top management.  The outputs of any such exercise are therefore constrained to those that are acceptable to top management.  Hence the nature of the ‘participation’ and the outputs are both highly controlled.  This may lead many ‘participants’ to suspect that the real agenda is one of manipulation rather than genuine participation.  The second potential benefit of providing a more reflective means of decision-making will also rapidly disperse should the same approach be implemented time over again.  Once the structure of the exercise is allowed to become predictable, it will provide no more benefit than any other mechanistic ‘box-ticking’ exercise.

 

Unrealistic expectations

Some of the claims commonly made in support of risk and value management serve to create unrealistic expectations. The following quote from Don Ward, Chief Executive of the UK Construction Industry Board, is by no means unusual:

 

Techniques such as value management ensure better definition of needs and lead to fewer changes during the project. The result? A better product, typically, delivered ahead of programme (which in turn can mean earlier business income, for example, to a retail client), with improved cost certainty and lower whole-life costs.”  [34]

 

Unfortunately, the techniques of value management are not capable of ‘ensuring’ anything.  Techniques do not have any meaning in isolation of the way in which they are enacted, and people enact value management in different ways.  There is no established causal link between the use of value management and a resulting better product.  So-called improvement techniques such as value management can only meaningfully be evaluated in terms of whether or not the participants found the process to be useful.  Much clearly depends upon the rhetoric used initially to justify the use of value management and the subsequent degree of post hoc rationalisation.  Furthermore, there is no consensus on which techniques constitute value management.  It would seem that Ward [34], the Construction Industry Board [1], and others, have fallen victim to the propaganda of those who wish to propagate value management for their own purposes. 

            Ward’s [34] naive faith in value management is perhaps indicative of the Western world’s general weakness for management panaceas.  Managers everywhere feel overwhelmed by uncertainty and struggle to exert control over their day-to-day environment.  They are therefore desperate for any promise of a ‘quick fix’.  The result is that the construction industry becomes ever more desperate as it lurches from one improvement technique to another.  Total quality management, business process re-engineering, value management, risk management and lean thinking are all held up in turn to be the saviour of the construction industry.  All are notoriously amorphous constructs that are strong on rhetoric and weak on coherence.  Managers seem to have an in-built weakness for the rhetoric of reductionalist management improvement recipes.  The construction industry would surely be better served by more thoughtful managers who recognise that uncertainty cannot be ‘managed away’ by a programmed technique.

 

 

THE DRAMATURGICAL METAPHOR

 

The concept of gaining insights into managerial practice through the use of metaphors was popularised by Morgan [35]. Although the roots of the dramaturgical metaphor can be traced back as far as Goffman [36], the notion that ‘management’ can usefully be perceived as a performing art owes much to Mangham [37]. Clark and Salaman [38] have since examined management consultancy from a dramaturgical perspective, that is, they argue that insights can be gained by thinking in terms of the consultant’s performance in front of a client. The way in which value management, and increasingly risk management, evolve around participative workshops makes the dramaturgical metaphor especially powerful.  The conceptualisation is that the facilitators attempt to create a reality for their audience (i.e. the client) which captures their imagination and commitment. All participants are assigned roles that are acted out in accordance with a previously agreed script. The success of the facilitator is primarily judged in terms of her performance.

            The performance is initially commissioned by the client in accordance with the accepted scripts on how ‘best practice’ clients should behave, e.g. [1]. The decision to implement risk/value management is therefore the outcome of a previous ‘act’ in the drama of management. The client’s representative would be required to act out the expected role of a project manager. As an effective project manager, she would be expected to instigate the latest management ideas, including risk management and value management. Given that these are conceptualised in the literature entirely separately, the expectation would be that they should be performed separately.

 

The drama of value management

If the client’s representative decided initially to act out value management, she would read some of the readily available publications before approaching a number of consultants.  The consultants would act out the role of appearing authoritative and would confidently describe the services that they have to offer.  Note that the consultant would ‘tell a different story’ depending on which school of thought they subscribed to.  Advocates of Barton [11] would use a different language from the advocates of SAVE International [9]. The language would be different because they would be talking from different scripts.  Once commissioned, there would be an expectation that the consultant would perform in accordance with the agreed script.  If she had emphasised the use of ‘function analysis’ in her initial interview, she would be expected to perform ‘function analysis’ in the workshop.  Briefing notes would be sent to the intended participants emphasising what their roles in the drama would be.  On the day of the workshop, the drama would be enacted.  The facilitator would arrive with the necessary ‘props’: coloured pens, bluetac and flipcharts. All parties would then act out roles in accordance with the script, hopefully leaving some scope for improvisation.  The facilitator would be highly animated, usually waving her arms about a good deal.  She would steer the workshop through the various stages of the script.  The closing act would invariably be the formulation of an ‘action list’. 

 

The drama of risk management

Given the previous contention that there is no substantive difference between risk management and value management, it would be reasonable to suppose that the enactment of a risk management workshop would be broadly similar to that described above. The main difference would lie in the language dictated by the alternative script.  Whereas a value management facilitator would say the words ‘value’ and ‘function’ often and loudly, a risk management facilitator would rely on phrases such as ‘risk identification’ and ‘risk response’.  Both would share the same practical reliance on coloured pens, bluetac and flipcharts. The ‘outputs’ of each workshop would be shaped by the language of their respective scripts.  These would in turn shape the expectations for some subsequent ‘act’ in the on-going management drama.

            The preceding interpretation is admittedly more reflective of the ‘soft’ approaches to risk management which are enacted through participative workshops.  Nevertheless, the ‘hard’ quantitative approach can also be conceived in terms of a performance, albeit to a different script.  For example, a practitioner who followed the script provided by Chapman and Ward [16] would be expected to play the role of ‘rational calculator’.  Key props would include a laptop computer and risk analysis software.  The initial consultations would contain their own elements of drama, before the consultant withdraws to complete the ‘analysis’ (also a necessary part of the drama).  A further act of drama would follow when the consultant presents the ‘findings’ to the client. The action taken would be primarily dependent on the persuasiveness of the consultant’s rhetoric.  Note that no risk assessment exercise can ever be ‘complete’.  Constraints are always imposed by the resources available to conduct the analysis and the unavoidable limitations of bounded rationality. The rigour of any risk assessment exercise is therefore ultimately judged in terms of the currently accepted standard.  In other words, it is the standard that provides the script for the justification. Note also that such standards are themselves socially negotiated and that the requirements of rigour change over time.  For example, in the nuclear industry there have been numerous examples of risk assessment exercises which, whilst persuasive at the time, have seemed much less than persuasive in retrospect.

 

           

TOWARDS AN INTEGRATED SCRIPT

 

The language of uncertainty

The first step towards an integrated script for risk and value management is to reject the language of ‘risk’ and ‘value’ in favour of the language of uncertainty.  Value management is primarily concerned with resolving uncertainty regarding project objectives.  In contrast, risk management addresses uncertainty regarding outcomes.  When expressed in these terms, the inter-dependence between risk and value management is readily apparent.  The effect of unknown outcomes cannot be assessed until the objectives are clear.  At the same time, the project objectives may well depend upon the identified areas of uncertainty.  A feasible script that addresses both types of uncertainty is provided by the group decision support methodology known as ‘strategic choice’.

 

Strategic choice  

Strategic choice is rooted in the socio-technical approach pioneered by the Tavistock Institute during the 1970s. The approach is facilitator-driven with no specific constraints regarding the number or length of workshops. The description that follows is primarily derived from Friend and Hickling [39] and Friend [40].

     The basic premise of strategic choice is that managerial decisions are made in conditions of uncertainty.  It seeks to aid the decision-making process by conceptualising three different types of uncertainty, the first of which relates to the clarity of ‘guiding values’.  This type of uncertainty, labelled UV, is primarily caused by ambiguous objectives.  A decision-making group’s response to UV may be to seek policy guidance from a higher authority, or to commission a consensus-building exercise such as a value management exercise.  The second type of uncertainty pertains to the broader environment and is labelled UE.  This is the kind of uncertainty which is normally dealt with through risk management  techniques.  Responses to UE are usually of a technical nature, comprising surveys, forecasting exercises or cost estimations [40].  The third kind of uncertainty concerns ‘related decision fields’.  This is labelled UR and relates to the ‘inter-connectiveness’ between decision areas.  In other words, uncertainty concerning the wider implications of an individual decision. The response here may be to re-frame the decision area or to consult with others beyond the immediate constituency of the problem-owners. 

            The conceptualisation of three different kinds of uncertainty is useful in that it provides a framework that subsumes not only the current practice of value management, but also that of risk management. However, neither of these two existing scripts gives explicit recognition to UR as a distinct area of uncertainty. Strategic choice makes explicit all three types of uncertainty and deals with them through an iterative decision-making process. Implementation is framed around four complementary modes of decision-making activity.

            The first mode, described as the shaping mode, is concerned with problem formulation. Key techniques include the graphical identification of, and linkage between, decision areas. This enables the decision-makers to identify the most urgent problems and agree upon an initial problem shape.  The second mode is labelled the designing mode during which the facilitator steers the participants towards the identification of different options. Of particular importance is the grouping of different combinations of options into discreet decision schemes. It is recognised that whilst some options would be compatible, others would be mutually exclusive. The third mode is the comparing mode and consists of a sequence of techniques that seek to compare the benefits of alternative decision schemes.  These techniques differ from those of decision analysis in that they allow for a combination of quantitative and qualitative comparison. The final stage of strategic choice is described as the choosing mode and is concerned both with making immediate decisions and with devising a strategy for managing those decisions which are best made in the light of further information. The outcome of any particular meeting would therefore always include immediate commitments to action and also strategies for resolving identified areas of uncertainty to aid future decisions. The latter aspect has some commonality with the established practice of maintaining risk registers.

            In advocating the 'use' of strategic choice it is important not to repeat the grandiose claims made in support of more prescriptive methodologies. Friend and Hickling [39] recognise that the established decision-making norms of linearity, objectivity, certainty and comprehensiveness inevitably break down when faced with real-world problems. The strategic choice approach is characterised by less simple prescriptions [39]:

 

·        Don't aim for linearity - learn to work with cyclicity.

·        Don't aim for objectivity - learn to work with subjectivity.

·        Don't aim for certainty - learn to work with uncertainty.

·        Don't aim for comprehensiveness - learn to work with selectivity.

 

The prime issue of importance is the way in which the embedded language of the strategic choice approach provides a different script for facilitated interventions. The language of uncertainty can serve to combine the separate story lines of risk and value management. The intervention can be justified in terms of the language of uncertainty. The workshop can be enacted and the outcomes justified in the same language. Whilst the strategic choice approach has appropriated numerous techniques associated with the four specified modes of decision making, it must be recognised that these techniques are inseparable from their embedded language. From a postmodernist perspective, a new technique is only useful in helping participants think differently because the language and imagery are unfamiliar. Once the techniques become familiar, they cease to stimulate different ways of thinking and therefore too easily regress to mechanistic exercises of dubious value. The metaphor of a facilitated workshop as an act of drama remains important. Given that so many risk (and value) workshops result in few tangible outcomes, it is important that the 'drama' engages project stakeholders as active participants rather than members of a passive audience. The intention must be to ensure that the process is 'on-line'. Too many existing value management exercises take place 'off-line' with little impact on day-to-day project management.  This is probably even more true in the case of risk management.

 

CASE STUDIES

 

The author has to date used the ‘uncertainty script’ of strategic choice on six separate occasions in a variety of different project contexts. Within the confines of this paper it is not possible to describe each occasion in detail. Nevertheless, it is possible to communicate the essence of what took place. Each project comprised an action-research intervention that sought to help with real-world projects. The six projects can be summarised as follows:

 

·        PFI submission for a Schools project;

·        Master planning exercise for the re-development of a major university campus;

·        £100M mixed retail and residential development in central London;

·        New supermarket development;

·        Major highways scheme.

·        A national programme of high street shop conversions.

 

Three of the above were billed as 'value management' and three were billed as 'risk management'. Each intervention consisted of a series of briefing meetings followed by a one-day facilitated workshop. The same approach was adopted irrespective of how the workshop was billed. The workshops were deliberately light on formal methodology whilst being loosely informed by the strategic choice framework. The sessions were facilitated in a positive manner whilst avoiding any tendency to impose solutions. Indeed, the facilitator avoided any temptation even to suggest courses of action. Each workshop involved a broad cross-section of stakeholders; numbers varied from twelve to twenty-seven.  The workshops would typically begin by asking the participants to state their four key issues of concern. These were written onto a post-it note that was then attached to a display board. The post-it stickers were then grouped into 'problem areas' that provided the agenda for the rest of the day. In broad terms, the groups were then sub-divided into three smaller groups on a forty-five minute cycle. Initially the groups were tasked to diagnose why the identified 'problem area' was problematic. Each group appointed their own facilitator who subsequently acted a spokesperson. The groups were asked to ensure that everything that they considered important was written down on their flipchart. After forty-five minutes (or so) the main workshop reconvened and the three presentations were made in turn. After the resultant discussion, the agenda for the next cycle was agreed and the workshop was again sub-divided into separate groups. Sometimes the groups were the same as previously, sometimes they were re-constituted. More often than not the focus of the second cycle was directed towards the production of recommendations. The facilitator endeavoured to be neutral at all times and deliberately avoided introducing any unfamiliar language, although he did often build on the discussion of the group. The three categories of UV, UE and UR were occasionally used as prompts for different sub-groups to identify different sources of uncertainly.  On each occasion the last session of the workshop was devoted to the derivation of an 'action list' to which specific responsibilities were assigned.

            The staged outcomes of the workshops were recorded on flipcharts and summarised in a brief written report. On all six occasions the scripts were accepted by the audience and the resultant ‘performance’ was well received.  Whilst the enactment of the workshops was loosely structured around the strategic choice methodology, the adopted approach was essentially pragmatic. However, the justification of the events depended upon the broader theoretical conceptualisation that underpins strategic choice. This provides a practical manifestation of the dramaturgical metaphor described previously. It was noticeable that the different sub-groups frequently resorted to the language of risk management, rarely did the terminology of value management provide the basis for discussion. It should also be added that many of the workshops participants were very experienced in the established approaches to risk management. Without exception, such participants were warmly supportive of the adopted approach. They were often especially complementary about the highly participative style of the events and the way in which the detailed agenda was formulated on the day. The relative absence of quantitative analysis was seen to be a strength rather than a weakness. Effective risk management is of course dependent upon quantitative assessments, but the view was accepted that such assessments are best carried once the overall 'problem frame' has been established.

            Future publications will described the workshops and resultant feedback in further detail. For the present, suffice it to say that there is evidence that the strategic choice approach can provide a feasible integrated script that embraces the story lines of both risk management and value management.  The adoption of the dramaturgical metaphor however militates against any grandiose claims on the behalf of ‘methodology’. The intention must be to propagate a more thoughtful approach to the management of uncertainty, rather than laying claim to yet another panacea.

 

 

CONCLUSION

 

This paper has presented a new way of thinking about risk and value management. It has been suggested that the current literature propagates a false distinction between these two activities. An alternative integrated script based on the strategic choice approach has been suggested. The legitimacy of this approach has been established through six action-research interventions. However, it has also been suggested that the relationship between a published ‘methodology’ and what happens in practice is much weaker than is commonly supposed.  From a postmodernist perspective, the prime contribution of a methodology is the way in which the adopted discourse shapes practice.  The initial need for a management-type intervention will be justified in terms of the rhetoric of the favoured methodology.  The text of the methodology will then provide the script for the enactment of the ‘drama’.  The rhetoric of the methodology will subsequently be used for the post hoc rationalisation of what took place.  However, the dramaturgical metaphor cannot provide a complete explanation of the way in which methodologies are enacted.  To make such a claim would be contrary to the adopted postmodernist position.  The insights achieved are inevitably incomplete and distorted by the adopted metaphorical lens.  In contrast to popularist management gurus, academics must always be aware of the limitations of their adopted standpoint.  It is notable that several authors readily concede the limitations of ‘mechanistic, checklist approaches to risk analysis’ and claim no monopoly on the truth.  Different insights are gained from different perspectives.  Each way of seeing is also a way of not seeing.  Perhaps the most important aspect of thinking in terms of metaphor is the way in which any one chosen metaphor exposes the limitations of others.  This awareness of the incompleteness of metaphor therefore fosters a healthy cynicism of all metaphorical approaches, be they implicit or explicit. A postmodernist position requires a continual process of reality deconstruction and reconstruction [35].  The benefits of this process have been demonstrated in the case of risk and value management. However, there is a danger that the strategic choice approach might be routinised through regular use. A continuous process of deconstruction and reconstruction is necessary to guard against this possibility. Indeed, it is contended that this cycle of intellectual activity is vital to continued innovation. It is also possible to make the argument that a greater understanding of metaphor and postmodernism amongst managers in the construction industry would serve to make them more creative and less susceptible to the mindless ideology of management panaceas. To promote a more thoughtful industry must surely be the prime responsibility of construction academics.

 

 

ACKNOWLEDGEMENTS

 

The research described was supported by the UK's Engineering and Physical Sciences Research Council (GR/M42657). The fieldwork and empirical analysis was conducted with the assistance of Ian Compson. An earlier version of this paper was presented at the 1999 CIB W-55 and W-65 Joint Triennial Symposium in Cape Town, South Africa. The author is grateful for the subsequent feedback from conference participants.

 

 

REFERENCES

 

1.           Construction Industry Board (1997) Constructing Success: Code of Practice for Clients in the Construction Industry, Thomas Telford, London.

2.           HM Government (1995) Setting New Standards: A Strategy for Government Procurement, Cm 2840, HMSO, London.

3.           Godfrey, P. S. (1996) Control of Risk: A Guide to the Systematic Management of Risk from Construction, Construction Industry Research and Information Association, London.

4.           HM Treasury (1993) Managing Risk and Contingency for Works Projects, CUP Guidance Note No. 41, Central Unit on Procurement, HM Treasury, London.

5.           Connaughton J. N. and Green, S D. (1996) Value Management in Construction: A Client’s Guide, Construction Industry Research and Information Association, London.

6.           HM Treasury (1996) Value Management, CUP Guidance Note No. 54, Central Unit on Procurement, HM Treasury, London.

7.           Dell'Isola, A. (1982) Value Engineering in the Construction Industry, 3rd edn., Van Nostrand Reinhold, New York.

8.           Miles, L. D. (1972) Techniques for Value Analysis and Engineering, 2nd edn., McGraw-Hill, New York.

9.           SAVE International (1997) Value Methodology Standard, SAVE International, USA.

10.       Green, S. D. (1994) Beyond value engineering: SMART value management for building projects, International Journal of Project Management, Vol. 12, No. 1. pp. 49-56.

11.       Barton, R. T (1996) The application of value management to the development of project concepts, in Proc. CIB W-65 International Symposium, Organisation and Management in Construction: Shaping Theory and Practice, (eds. D. A. Langford and A. Retik), Vol. 2, E & FN Spon, London, pp. 115-123.

12.       Kelly, J. and Male, S. (1993) Value Management in Design and Construction: The Economic Management of Projects, E. & F.N. Spon, London.

13.       Green, S. D. and Simister, S. J. (1996) Group decision support for value management, in The Organisation and Management of Construction, (eds. D. A. Langford and A. Retik), Vol. 2, E. & F.N. Spon, pp. 529-540.

14.       Rosenhead, J. (1989) Introduction: old and new paradigms of analysis, in Rational Analysis for a Problematic World: Problem Structuring Techniques for Complexity, Uncertainty and Conflict, (ed. J. Rosenhead), Wiley, Chichester, pp. 1-20.

15.       Checkland, P. B. (1981) Systems Thinking, Systems Practice, Wiley, Chichester.

16.       Chapman, C. and Ward, S. (1997) Project Risk Management, Wiley, Chichester.

17.       Flanagan, R. and Norman, G. (1993) Risk Management and Construction, Blackwell Science, Oxford.

18.       Raftery, J. (1994) Risk Analysis in Project Management, E & FN Spon, London.

19.       von Neumann, J. and Morgenstern, O. (1947) Theory of Games and Economic Behavior, 2nd edn., Princeton University Press, Princeton, NJ.

20.       Akintoye, A. S. and MacLeod, M. J. (1997) Risk analysis and management in construction, International Journal of Project Management, Vol. 15, No.1. pp. 31-38.

21.       Stevens, D. (1996) Strategic Thinking, McGraw-Hill, Roseville, Australia.

22.       Mak, S. W. (1995) Risk analysis in construction: a paradigm shift from a hard to soft approach, Construction Management and Economics, Vol. 13, No. 5. pp. 385-392.

23.       Simon, H. A. (1981) The Sciences of the Artificial, 2nd edn., MIT Press, Cambridge, Mass.

24.       Guba, E. G. and Lincoln, Y. S. (1998) Competing paradigms in qualitative research, in The Landscape of Qualitative Research: Theories and Issues (eds. Denzin, N. K. and Lincoln, Y. S.) Sage, Thousand Oaks, CA.

25.       Cherns, A. B. and Bryant, D. T. (1984) Studying the client's role in construction management, Construction Management and Economics,  Vol. 2, No. 2. pp. 177-184.

26.       Fishburn, P. C. (1970) Utility Theory for Decision Making, Wiley, New York.

27.       Institution of Civil Engineers (1996) Creating Value in Engineering, Thomas Telford, London.

28.       Ellsberg, D. (1954) Classic and current notions of "measurement utility", Economic Journal, Vol. 64. pp. 528-556.

29.       Edwards, W. (1954) The theory of decision making, Psychological Bulletin, Vol. 51. pp. 380-417.

30.       von Winterfeldt, D. and Edwards, W. (1986) Decision Analysis and Behavioral Research, Cambridge University Press, Cambridge.

31.       Hassard, J. (1994) Postmodernism and organizational analysis: an overview, in Postmodernism and Organizations, (eds. J. Hassard and M. Parker), Sage, London, pp. 1-23.

32.       Legge, K. (1995) Human Resource Management: Rhetorics and Realities, MacMillan, Basingstoke.

33.       Cooper, R. and Burrell, G. (1988) Modernism, postmodernism and organizational analysis: an introduction, Organization Studies, Vol. 9, No. 1. pp. 91-112.

34.       Ward, D. (1998) When it comes to costs, get your terminology right, letter to Building, 3 July, pg. 31.

35.       Morgan, G. (1986) Images of Organization, Sage, London.

36.       Goffman, E. (1959) The Presentation of Self in Everyday Life, Doubleday, Garden City, NY.

37.       Mangham, I. L. (1990) Managing as a performing art, British Journal of Management, Vol. 1. pp. 105-115.

38.       Clark, T. and Salaman, G. (1996) The use of metaphor in the client-consultant relationship: A study of management consultancies, in Organization Development: Metaphorical Explorations, (eds. C. Oswick and D. Grant), Pitman, London, pp. 154-174.

39.       Friend, J. K. and Hickling, A. (1997) Planning under Pressure: the Strategic Choice Approach, 2nd edn., Butterworth-Heinemann, Oxford.

40.       Friend, J. K. (1989) The strategic choice approach, in Rational Analysis for a Problematic World: Problem Structuring Techniques for Complexity, Uncertainty and Conflict, (ed. J. Rosenhead), Wiley, Chichester, pp. 121-157.